Migration Implementation
|
|
~~~~~~~~~~~~~~~~~~~~~~~~
|
|
|
|
Migration Team Establishment
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
A large-scale migration project usually involves migration of a large
|
|
number of applications in a short period of time and complex
|
|
cross-application troubleshooting. The project management offices (PMOs)
|
|
will take the lead, and organize and arrange personnel from both parties
|
|
to carry out related work in an orderly and efficient manner based on
|
|
the project objectives.
|
|
|
|
T-Systems and the customer, need to set up their own project teams based on
|
|
Open Telekom Cloud's Customers Success Engineers experience in cloud migrations.
|
|
The two teams will work together during the migration.
|
|
|
|
The following figure shows the structure of the recommended migration team:
|
|
|
|
.. image:: ../../assets/caf/image49.png
|
|
|
|
- Project manager (PM): The PM sets up a joint project PMO to manage
|
|
project progress, identify and manage risks and other issues, and
|
|
promote the project within the organization.
|
|
|
|
- Architecture and migration implementation team: The team designs
|
|
solutions for cloud migration and cutover, manage and implement
|
|
migration, and control technical risks during the implementation.
|
|
|
|
- Test team: The team tests solutions and performs function,
|
|
performance, and joint commissioning tests.
|
|
|
|
- O&M team: The team creates, manages, and monitors cloud resources.
|
|
|
|
- Migration and R&D support team (Open Telekom Cloud): The team processes
|
|
escalated technical issues.
|
|
|
|
- Development team (customer): The team is responsible for application
|
|
development, deployment, and migration.
|
|
|
|
Migration Assurance
|
|
^^^^^^^^^^^^^^^^^^^
|
|
|
|
- Project kick-off meeting: A formal project kick-off meeting is
|
|
initiated to specify the project scope, objectives, delivery period,
|
|
and responsibilities.
|
|
|
|
- Project communication management: Regular communication is important
|
|
between project members and project stakeholders. Communication
|
|
exposes and helps address potential issues.
|
|
|
|
- Project progress management: The execution of project activities and
|
|
key tasks is monitored to ensure that the project progresses as
|
|
planned. If there is a deviation from the schedule, corrective
|
|
measures will be taken and reported to project members and
|
|
stakeholders in the form of weekly or daily reports.
|
|
|
|
- Issue and risk management: Project assumptions and risks are
|
|
continuously monitored to quantify risks. The risk management plan
|
|
may need to be updated at time and the implementation of risk
|
|
mitigation measures needs to be ensured. Issues and risks are
|
|
recorded and tracked, including details such as the issue owners and
|
|
the times when the issues were identified. These details then need to
|
|
be reported to project members and other stakeholders in the form of
|
|
weekly or daily reports.
|
|
|
|
- Delivery matrix: A joint project delivery matrix covering Open Telekom
|
|
Cloud and the customer will be developed.
|
|
|
|
Testing and Verification
|
|
^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Before services are cut over to the cloud, functional and performance
|
|
tests will be performed to verify that the applications are stable in
|
|
the cloud environment.
|
|
|
|
Service function testing
|
|
************************
|
|
|
|
The Open Telekom project personnel use the cloud resource list to make sure
|
|
all the required resources on Open Telekom Cloud are enabled. They initialize
|
|
environment configurations, deploy applications, and migrate some data
|
|
to perform joint commissioning tests. After the environment is deployed,
|
|
customers can use their own test cases to test applications and confirm
|
|
that services can run properly on the cloud.
|
|
|
|
Performance testing
|
|
*******************
|
|
|
|
Performance testing tests not just performance. There are also load
|
|
testing, pressure testing, and stability testing. Performance testing
|
|
means continuously raising the access pressure on the system (in a
|
|
system test environment, the number of concurrent requests is constantly
|
|
increasing for the test program) to obtain system performance KPIs and
|
|
maximum load-bearing capacity.
|
|
|
|
For performance testing, you can select JMeter or any other offering that
|
|
supports JMeter test projects or use third-party pressure test tools.
|
|
|
|
.. tip::
|
|
|
|
JMeter (for simulating user traffic) and TCPCopy or GoReplay
|
|
(for recording or copying real user traffic) can be used to perform
|
|
pressure testing on all-link applications on the cloud to check whether
|
|
functions and performance meet requirements.
|
|
|
|
During the test, test records and reports are generated based on the
|
|
monitoring metrics of Open Telekom Cloud monitoring systems (such as CES, AOM,
|
|
APM) and the customer's monitoring systems as well as application logs.
|
|
|
|
After the pressure test is complete, the dirty data generated during the
|
|
test is deleted, and a full and incremental data migration is performed.
|
|
After the migration is complete, at an appropriate time, service traffic
|
|
is switched over to the application on the cloud.
|
|
|
|
Service Cutover and Rollout
|
|
^^^^^^^^^^^^^^^^^^^^^^^^^^^
|
|
|
|
Service cutover and rollout are the most critical steps in a cloud
|
|
migration. Any issues in this step may lead to major faults. To ensure
|
|
smooth service cutover and rollout, a detailed pre-cutover checklist
|
|
must be formulated.
|
|
|
|
After the service cutover is complete, service running and data are
|
|
continuously monitored and observed until the services are stable on the
|
|
cloud.
|
|
|
|
After the final data synchronization is complete and dirty data
|
|
generated during testing is deleted from the target environment on
|
|
Open Telekom Cloud, service cutovers are started in off-peak hours. Generally,
|
|
service cutover can be implemented all at once, or layer by layer.
|
|
|
|
All at once
|
|
***********
|
|
|
|
For a simple or small-scale system, as long as a
|
|
full-service verification is performed first, the cutover can be
|
|
completed at a time. This kind of cutover is fast and has little
|
|
impact on ongoing services.
|
|
|
|
The one-off cutover process is as follows:
|
|
|
|
.. image:: ../../assets/caf/image50.png
|
|
|
|
1. Stop the tests on the target and delete the test data.
|
|
2. Stop the services on the source.
|
|
3. Complete the incremental data synchronization.
|
|
4. (Optional) Configure reverse data synchronization to prepare for a rollback in case the cutover fails.
|
|
5. Modify the DNS configuration, switch the EIP, and switch traffic to the target.
|
|
6. Observe the service stability on the target.
|
|
7. Provide continuous assurance.
|
|
|
|
Layer by layer
|
|
**************
|
|
|
|
For complex services or large-scale systems, services
|
|
can be decoupled and cut over layer by layer. If there are any
|
|
problems, a rollback can be performed for an individual layer, which
|
|
reduces the risk of impacting services. However, a hierarchical
|
|
cutover like this requires multiple cutovers, which are
|
|
time-consuming and involve a heavy workload.
|
|
|
|
Layer-by-layer migration consists of two steps. First, the application
|
|
layer is cut over to Open Telekom Cloud, but with the service data still being
|
|
read from and written to on the source. After the application layer
|
|
cutover is complete, a data migration or application dual-write is
|
|
performed to synchronize service data from the source to the target on
|
|
Open Telekom Cloud in real time. After the incremental data migration is
|
|
complete, the second step, the data layer cutover, will be executed.
|
|
|
|
Layer-by-layer migration involves cross-cloud database access. The
|
|
network latency needs to be evaluated to see if it meets application
|
|
requirements.
|
|
|
|
The layer-by-layer cutover process is as follows:
|
|
|
|
.. image:: ../../assets/caf/image51.png
|
|
|
|
Step 1: Application layer cutover
|
|
+++++++++++++++++++++++++++++++++
|
|
|
|
a. Stop the tests on the target and delete the test data.
|
|
b. Modify the configuration of the middleware layer on the target to
|
|
point to the data layer on the source (through Direct Connect or
|
|
VPN connections).
|
|
c. Modify the DNS configuration, switch the EIP, and switch traffic to
|
|
the target.
|
|
d. Observe the service stability on the target.
|
|
|
|
Step 2: Database layer cutover
|
|
++++++++++++++++++++++++++++++
|
|
|
|
a. Stop the services on the target.
|
|
b. Complete the incremental data synchronization.
|
|
c. (Optional) Configure reverse data synchronization to prepare for
|
|
rollback upon migration failure.
|
|
d. Modify the configuration of the middleware layer on the source to
|
|
point to the data layer on the target.
|
|
e. Start services on the target.
|
|
f. Observe the service stability on the target.
|
|
g. Provide continuous assurance.
|
|
|
|
Cutover risks and service rollback
|
|
**********************************
|
|
|
|
The rollback solution in the all-at-once cutover scenario is simple.
|
|
This section describes the rollback solution in the layer-by-layer
|
|
cutover scenario.
|
|
|
|
.. image:: ../../assets/caf/image52.png
|
|
|
|
Rollback solutions in the hierarchical cutover scenario are different
|
|
if:
|
|
|
|
The data layer has not been cut over
|
|
++++++++++++++++++++++++++++++++++++
|
|
|
|
You can directly switch the DNS to switch traffic back to the source
|
|
system.
|
|
|
|
The data layer has been cut over
|
|
++++++++++++++++++++++++++++++++
|
|
|
|
Step 1: Roll back the data layer
|
|
################################
|
|
|
|
a. Stop the services on the target.
|
|
b. Complete the reverse data synchronization.
|
|
c. Modify the configuration of the middleware layer on the target to
|
|
point to the data layer created after the reverse synchronization on
|
|
the source.
|
|
d. Start services on the target.
|
|
e. Observe the service stability.
|
|
|
|
Step 2: Roll back the application layer
|
|
#######################################
|
|
|
|
a. Modify the configuration of the middleware layer on the source to
|
|
point to the data layer created after the reverse synchronization on
|
|
the source.
|
|
b. Modify the DNS configuration, switch the EIP, and switch traffic to
|
|
the source.
|
|
c. Start services on the source.
|
|
d. Observe the service stability.
|
|
|
|
Assurance solution for seamless DNS switchover
|
|
**********************************************
|
|
|
|
After a public domain name record is modified, it needs to be delivered
|
|
to all DNS servers around the world. Due to certain restrictions
|
|
inherent to international basic network infrastructure, the modification
|
|
takes effect within 2 hours in the Chinese mainland, but takes 48 hours
|
|
outside the Chinese mainland. During this time, the domain name may be
|
|
resolved to the original IP address, resulting in access exceptions.
|
|
|
|
If the domain name is resolved to the original IP address because the
|
|
modification to the domain name resolution record has not taken effect,
|
|
you can deploy Nginx or iptables on the source and use the Nginx HTTP
|
|
proxy or the iptables NAT to forward traffic to Open Telekom Cloud, achieving
|
|
seamless switchover of domain name records.
|
|
|
|
The following uses Nginx HTTP proxy as an example to describe the
|
|
procedure for configuring traffic forwarding:
|
|
|
|
1. Before the switchover, deploy an Nginx reverse proxy server at the
|
|
back of the load balancer on the source to forward traffic to Open Telekom
|
|
Cloud ELB.
|
|
2. After the domain name is switched, bind the source domain name and IP
|
|
address to the load balancer.
|
|
3. The load balancer forwards the traffic to the backend Nginx server.
|
|
The backend Nginx server forward the traffic to the EIP of Open Telekom
|
|
Cloud ELB load balancer over the public network.
|
|
4. (Optional) Deploy traffic monitoring software (for example, ntop) on
|
|
the source Nginx server and view Nginx access logs. If no traffic is
|
|
generated and access logs are not updated, DNS resolution has been
|
|
switched over to Open Telekom Cloud.
|
|
5. Delete the load balancer and Nginx proxy server deployed on the
|
|
source.
|
|
|
|