Changing Specifications

If the workloads on the data plane of a cluster change, you can change its node specifications as needed.

Prerequisites

Constraints

Procedure

  1. Log in to the CSS management console.
  2. In the navigation pane, choose a cluster type. The cluster management page is displayed.
  3. Choose More > Modify Configuration in the Operation column of the target cluster. The Modify Configuration page is displayed.
  4. On the Modify Configuration page, choose the Scale Cluster tab and click Change Specifications to set parameters.
    • Action: select Change specifications.
    • Resources: The changed amount of resources.
    • Nodes: Specifications of the default data nodes. Select the required specifications from the Node Specifications drop-down list and select the node that you want to change the specifications.
    • If a cluster has master nodes, client nodes, or cold data nodes, you can change their specifications.
  5. Click Next.
  6. Confirm the information and click Submit.
  7. In the displayed Verify Index Copy dialog box, select Verify index copies if you need. Click OK.
    • If you selected Verify index copies and the cluster has no master node, indexes must have at least one copy and the cluster must have at least three nodes.
    • If you selected Verify index copies and the cluster has no master node, indexes must have at least one copy.
  8. Click Back to Cluster List to switch to the Clusters page. The Cluster Status is Configuration modified. When Cluster Status changes to Available, the cluster specifications have been successfully modified.